Files
rtu_v5/.planning/STATE.md
admin f50fdef263 docs(quick-2): complete quick task 2 - v1/v2 structure
- Summary: Archived Flask v1 to src_v1/, initialized v2 React from sample_interface
- Updated STATE.md with quick task 2 completion
2026-03-12 12:31:53 +08:00

2.6 KiB

gsd_state_version, milestone, milestone_name, status, stopped_at, last_updated, last_activity, progress
gsd_state_version milestone milestone_name status stopped_at last_updated last_activity progress
1.0 v1.0 milestone Phase 1 executed successfully Phase 3 context gathered 2026-03-12T12:30:00.000Z 2026-03-12 — Phase 1 complete
total_phases completed_phases total_plans completed_plans percent
4 2 3 3 100

Project State

Project Reference

See: .planning/PROJECT.md (updated 2026-03-12)

Core value: Real-time rainfall and environmental sensor monitoring with automatic data transmission to myvscada server Current focus: Phase 2: Data Persistence & File Management

Current Position

Phase: 1 of 4 (Foundation & Kiosk UI) - COMPLETE Phase: 2 of 4 (Data Persistence & File Management) - Ready to plan Status: Phase 1 executed successfully

Last activity: 2026-03-12 — Phase 1 complete

Progress: [██████████] 100%

Performance Metrics

Velocity:

  • Total plans completed: 1
  • Average duration: N/A
  • Total execution time: <1 hour

By Phase:

Phase Plans Total Avg/Plan
1. Foundation & Kiosk UI 1 1 <1h

Recent Trend:

  • Phase 1 completed successfully in <1 hour

Updated after each plan completion

Accumulated Context

Decisions

Decisions are logged in PROJECT.md Key Decisions table. Recent decisions affecting current work:

  • [Research]: Selected Flask + Flask-SocketIO + Bootstrap stack for Pi Zero 2 W performance
  • [Research]: Four-phase vertical slice approach based on dependency analysis
  • [Phase 1]: Implemented Flask backend with SocketIO for real-time sensor updates
  • [Phase 1]: Flask + SocketIO for real-time updates on resource-constrained Pi Zero 2 W

Pending Todos

[From .planning/todos/pending/ — ideas captured during sessions]

None yet.

Blockers/Concerns

[Issues that affect future work]

None yet.

Quick Tasks Completed

# Description Date Commit Directory
1 Add a logo to the app. Logo can be found in the logo folder 2026-03-12 d18ef95 1-add-a-logo-to-the-app-logo-can-be-found-
2 Store current Flask v1 interface as v1 and init v2 2026-03-12 de6e642 2-store-this-current-interface-as-v1-and-w

Session Continuity

Last session: 2026-03-12T03:09:14.375Z Stopped at: Phase 3 context gathered Resume file: .planning/phases/03-network-transmission/03-CONTEXT.md

Last activity: 2026-03-12 — Completed quick task 2: Store v1 & init v2