- Update ROADMAP.md with Phase 1 complete - Update STATE.md with progress and current focus - Create 01-SUMMARY.md with implementation details
1.5 KiB
Project State
Project Reference
See: .planning/PROJECT.md (updated 2026-03-12)
Core value: Real-time rainfall and environmental sensor monitoring with automatic data transmission to myvscada server Current focus: Phase 2: Data Persistence & File Management
Current Position
Phase: 1 of 4 (Foundation & Kiosk UI) - COMPLETE Phase: 2 of 4 (Data Persistence & File Management) - Ready to plan Status: Phase 1 executed successfully
Last activity: 2026-03-12 — Phase 1 complete
Progress: [█░░░░░░░░░] 25%
Performance Metrics
Velocity:
- Total plans completed: 1
- Average duration: N/A
- Total execution time: <1 hour
By Phase:
| Phase | Plans | Total | Avg/Plan |
|---|---|---|---|
| 1. Foundation & Kiosk UI | 1 | 1 | <1h |
Recent Trend:
- Phase 1 completed successfully in <1 hour
Updated after each plan completion
Accumulated Context
Decisions
Decisions are logged in PROJECT.md Key Decisions table. Recent decisions affecting current work:
- [Research]: Selected Flask + Flask-SocketIO + Bootstrap stack for Pi Zero 2 W performance
- [Research]: Four-phase vertical slice approach based on dependency analysis
- [Phase 1]: Implemented Flask backend with SocketIO for real-time sensor updates
Pending Todos
[From .planning/todos/pending/ — ideas captured during sessions]
None yet.
Blockers/Concerns
[Issues that affect future work]
None yet.
Session Continuity
Last session: 2026-03-12 Stopped at: Phase 1 complete - ready for Phase 2 Resume file: None