gsd_state_version: 1.0
|
|
milestone: v1.0
|
|
milestone_name: milestone
|
|
status: Phase 1 executed successfully
|
|
stopped_at: Phase 2 context gathered
|
|
last_updated: "2026-03-11T22:40:23.528Z"
|
|
last_activity: 2026-03-12 — Phase 1 complete
|
|
progress:
|
|
total_phases: 4
|
|
completed_phases: 1
|
|
total_plans: 1
|
|
completed_plans: 1
|
|
percent: 100
|
|
---
|
|
|
|
# Project State
|
|
|
|
## Project Reference
|
|
|
|
See: .planning/PROJECT.md (updated 2026-03-12)
|
|
|
|
**Core value:** Real-time rainfall and environmental sensor monitoring with automatic data transmission to myvscada server
|
|
**Current focus:** Phase 2: Data Persistence & File Management
|
|
|
|
## Current Position
|
|
|
|
Phase: 1 of 4 (Foundation & Kiosk UI) - COMPLETE
|
|
Phase: 2 of 4 (Data Persistence & File Management) - Ready to plan
|
|
Status: Phase 1 executed successfully
|
|
|
|
Last activity: 2026-03-12 — Phase 1 complete
|
|
|
|
Progress: [██████████] 100%
|
|
|
|
## Performance Metrics
|
|
|
|
**Velocity:**
|
|
- Total plans completed: 1
|
|
- Average duration: N/A
|
|
- Total execution time: <1 hour
|
|
|
|
**By Phase:**
|
|
|
|
| Phase | Plans | Total | Avg/Plan |
|
|
|-------|-------|-------|----------|
|
|
| 1. Foundation & Kiosk UI | 1 | 1 | <1h |
|
|
|
|
**Recent Trend:**
|
|
- Phase 1 completed successfully in <1 hour
|
|
|
|
*Updated after each plan completion*
|
|
|
|
## Accumulated Context
|
|
|
|
### Decisions
|
|
|
|
Decisions are logged in PROJECT.md Key Decisions table.
|
|
Recent decisions affecting current work:
|
|
|
|
- [Research]: Selected Flask + Flask-SocketIO + Bootstrap stack for Pi Zero 2 W performance
|
|
- [Research]: Four-phase vertical slice approach based on dependency analysis
|
|
- [Phase 1]: Implemented Flask backend with SocketIO for real-time sensor updates
|
|
- [Phase 1]: Flask + SocketIO for real-time updates on resource-constrained Pi Zero 2 W
|
|
|
|
### Pending Todos
|
|
|
|
[From .planning/todos/pending/ — ideas captured during sessions]
|
|
|
|
None yet.
|
|
|
|
### Blockers/Concerns
|
|
|
|
[Issues that affect future work]
|
|
|
|
None yet.
|
|
|
|
## Session Continuity
|
|
|
|
Last session: 2026-03-11T22:40:23.524Z
|
|
Stopped at: Phase 2 context gathered
|
|
Resume file: .planning/phases/02-data-persistence-file-management/02-CONTEXT.md
|